can anybody tell me in detail what the configuration we have to do in MRP.


Dear Avi raina,

MD01 for a full run by plant

MD02 and MD03 to run MRP for one material

MD01 - MRP Run

MD02 - MRP - Single-item, Multi-level

MD03 - MRP-Individual Planning-Single Level

MD04 - Display Stock/Requirements Situation

MD05 - Individual Display Of MRP List

MD06 - Collective Display Of MRP List

MD21 - Display Planning File Entry

The mandatory fields you need maintain are all MRP views in material master with valid MRP type normally "PD".

You can run MRP from

MD03 (for single item)

MD02 ( for complete BOM)

MD01 and MDBT (at plant level).

The control parameters should be:

Processing key: NETCH

Create PR/PO: 1

Create schedule lines: 3

create MRP list: 1

planning mode: either 1 or 3

Scheduling: 1

In process parameters do not check "simulation mode"

With regards,