Difference between Contract & Scheduling Agreement in SAP SD

Former Member

Hi Gurus,

What is the difference between Contract & Scheduling Agreement, in terms of Functionality?

Regards,

Vadivel

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi vadivel,

A schedule agreement contains details of a delivery schedule along with delivery dates

but

a contract just contains quantity and price information and no details of specific delivery dates

Thanks

Mohan

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

contract is an agreement between the customer and the company. It will have a validity date and the quantity or value. Based on the contract (Qty or value), orders will be created with reference to the contract and bill it, until the qty or value of the contract reached. It will not have a schedule line.

Scheduling agreement is also an agreement, the quantity will be devided into different schedule lines , and the delivery will be created based on these schedule line in the agreement.

The main different is contracts will not have schedule line, but scheduling agreement will have schedule lines.

Prase

0 Kudos

Hi,

In sch agre sch line will be there and system will check target qty with sch line qty.

del is created w.r.t sch agre.

where as in contract, no sch line. release order is used to release the contract item/value. and del, billing

former_member184555
Active Contributor
0 Kudos

Hi

In the case of contracts, the release order can be given on any dates till the contract expires.

In the case of Scheduling agreement- we give the delivery schedules in the agreement itself and we need not create any sales order/ release order. Based on the delivery date, it automatically gets included in the delivery due list.

Thanks,