Hello
Can anyone tell me what steps should I take to customize ECM (Engineering Change Management) to be able to use it with material BOMs ?
(All I need is just to be able to change the definitions of material BOMs in a way that saves the old definition - that is assign the old definition to some validity period and start a new definition valid since specific date.
As I found out it is possible only when you use "change number" which belongs to the functionality of ECM).
Thanks in advance
regards
Dear Maciej,
You have to do the following settings.
1.In OS54 - (SPRO - Logistics General - Engineering Change Management -Set
Control Data ) Do the necessary settings for Validity , Revision Level ,Release
ley,Date Shift.
2.In OS53 - Define Number Ranges for ECN's.
3.In OS27 - Define Modification Parameters for BOM'sinclude for EC Management
Active , History Requirement,BOM validity maintenance.
4.In OS25 - Configure History Requirements for BOM's.
If you can give me your mail id,I can send you some screen shots.
Regards
Mangal.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.