cancel
Showing results for 
Search instead for 
Did you mean: 

Copy cost centers & profit centers to a new Company

Former Member
0 Kudos

Hello,

What's the transactions or customizing path to copy cost and profit centers to a new company ?

Best reagards

Paul

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Paulo,

go to the standard hierarchy for cost center (t-code OKEON) then go to extras and transport Std. hierarchy same thing you can do for Profit centers.

Include the master data you want to include into the request.

it will solve your proble.

regards

abhay

Former Member
0 Kudos

Hello Abhay,

I don't want to transport to another system / client.

I want to copy from one controlling area to another.

Regards,

Paulo

Former Member
0 Kudos

You will probably need a LSMW.

If you are creating brand new Cost Centers and Profit Centers and moving them to a new Company Code, what are you going to do with the current set of master data.

You need to make sure you close them by changing their life.

KE56 moves profits centers from one company code to another one.

Former Member
0 Kudos

I just want to duplicate the structure displayed in OKENN transaction,

for cost centers

and the structure displayed in KCH6N transaction for profit centers,

to the new Company.

Any ideas ?

regards,

Paul

Former Member
0 Kudos

Hi,

Good evening and greetings,

Try using KE56.

Please reward points if found useful.

Thanking you,

With kindest regards,

Ramesh Padmanabhan

Former Member
0 Kudos

Hi Ramesh,

Thank you for your reply.

I Want to copy the structure of profit and cost centers from one Company to another (new).

Is this the right transaction ?

Regards

Paul