Hi gurus,

I have a problem in schedule lines. End user saved the document by mistake with requirement type 031 but it should be 011.Delivery done and PGI not done. How to change requirement type.Please help me.

Thanks&regards

madhu

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

delete delivery saved and change it.

Former Member
0 Kudos

on the basis of checking rule to plant and matrila type it will come what is the need of changing requirement type after pgi u can change in the sales order