hi

In material master for project material (special stock 'Q') price is not updated. it is right or wrong?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

The price will updated under project stock level, if you're using Material ledger, you can see it in CKM3.

Former Member
0 Kudos

no, material ladger is not active.we maintain the diff val type for project material, price should be updated at this val type level , for this material price is also not being updating. what is project stock level?

Former Member
0 Kudos

Please check to link below under project stock path, there's an explanation related:

http://help.sap.com/erp2005_ehp_02/helpdata/en/4d/4b9036dfe4b703e10000009b38f889/frameset.htm