Hi All,
My client want to post commitment costs only after creating PO's But they dont want commitment costs by creating PR's,How to do this.
Thanks
Muzamil
Hi
Commitment will be created when you create PR for project. The only way to avoid getting commitment for PR is to let MRP create PR, and in which case there would be no commitment for the Purchase requisitions.
Regards
Amal