on 10-16-2007 4:14 PM
Hi all,
Can any one tell me if it is possible to set two different safety stocks for two diffetent storage lacations for one materila?
If yes, How?
Thank you,
Utpal
Thank you, Points rewarded!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello UNP,
Normally, planning is useally carried out at plant level, however you can do MRP at Sloc level as well.
Safety stock is planning data which is defined for entire plant where as reorder level and replinishment quantity can be defined saperately for each storage location, but not safety stock.
hope this helps.
Regards
Arif Mansuri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.