Hi all,

Can any one tell me if it is possible to set two different safety stocks for two diffetent storage lacations for one materila?

If yes, How?

Thank you,

Utpal

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you, Points rewarded!

Former Member
0 Kudos

Hello UNP,

Normally, planning is useally carried out at plant level, however you can do MRP at Sloc level as well.

Safety stock is planning data which is defined for entire plant where as reorder level and replinishment quantity can be defined saperately for each storage location, but not safety stock.

hope this helps.