on 10-16-2007 1:17 PM
Hi Guys,
I have an activity in a network. While confirming an activity i have to enter both actual start date and end date. Is it possible to enter the actual start date alone at an instance and then enter actual finish date after a while(days) and confirm the activity when i enter actual finish date.
Ex. enter actual start date as today 16/10/2007 and enter actual finish date on 31/10/2007 and confirm an activity then.
Regards,
Paval.
Hai pavalavel,
In that case you can
1) Enter the starting date also on 31/10/07 and confirm it 100% totally on 31/10/07.i,e; you can do back confirmation
or
2)Enter partial confirmation say 5% or 10% with 16/10/07 as actual start date and confirm it totally 100% on 31/10/07.so that your dates will be as per your requirement.also you dont have to remember the actual start date. during the course of the activity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.