on 10-16-2007 12:15 PM
Hello,
my question is how to create a Master delivery plan to my customers manuelly and how to setup up it for to be able to create automatically the production planning orders.
Thank you kindly for you answers.
Hi
Create plan in MD61 .If you want date wise, week wise or monthly.
When you run MRP , planned orders will get created automatically.
Then you can go on converting planned orders to Production orders & execute the same.
Regards
YMREDDY