WO basic start date -> requirement date

mantas_andriekus
Participant
0 Kudos

Good morning folks,

Would anyone be able to shed some light on any config that would be suitable for the following:

The materials are assigned to a task list that is then assigned to a plan. That plan is then scheduled and the work orders are generated.

When the materials are added to the work order their requirement date is automatically assigned as the work order basic start date - can this requirement date be pulled from the scheduled dates instead?

The problem is that the material may not be required at the beginning of the WO, so the defaulted basic start date of the WO would not be the way forward.

Thanks

Mantas

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi Mantas

you can set in scheduling parameters with following possibilities

<b>Path Plant maintenance and customer service->Maintenance and service order->scheduling->set scheduling parameter</b>

1)The basic dates are adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.

2)The basic dates are not adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.

3)The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.

4)The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.

so when you add the components you have to assign the operations,after selecting the operation you can change the operation date, after you change the operation dates,the material scheduled dates will be changed to the operation date

(using the option <b>1</b>)

regards

thyagarajan

mantas_andriekus
Participant
0 Kudos

Perfect Thyagarajan, thank you.

Mantas