Budget Supplement


Can the budget supplement be distributed to the lower level WBS elements or the supplement should be done to the WBSE in need even if it is the lowest level WBSE?




Dear Amala

SAP distinguishes two type of supplements 1) To Project 2) In Project

If the budget supplement is "to the project (direct)" then use Tcode:CJ36, wherein u can give budget only to Top level WBS Elements only (exception : Invesment Management Budgeting)

If the budget supplement is "in the project(from top level to lower level)" then use Tcode:CJ37, wherein u can supplement the lower level WBS Elements.

Reward if useful