We have service and sales order that have settlement rule PSG. At settlement an FI posting is made, which are defined in OKG8.
PA uses the Cost elements (890963) assigned in OKG4 as the source. The PA transfer structure is complete - assigning values to Value Fields (VVC10)
When this settlement is complete - a Secondary Cost element is assigned to the settlement transaction (870200) and I see it in the Cost Analysis of the Orders
Where is this secondary cost element (870200) assigned?
thanks in advance for help
Althea
Found the answer - Allocation Structure which is under Cost object controlling > Period End > Settlement