on 10-15-2007 5:17 PM
Hi all,
I have maintained stop release if there is a capacity constraint and material shortage.
System is working fine for individual orders (C002) however if i am executing mass processing (CO05N) system is giving message for material shortage , but no message for capacity constraint.
Please guide.
Sipra
Hi Sipra
Did you maintain in OPJK capacity check , if you have given it shd message for capacity also
Cheers
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sipra,
Have you maintained "3" for Capacity in Check Control or "1", I think you have maintained one, since it is mass processing user interaction/interface does not take place and system releases with just a message in the logs for mass processing.
Please change the setting to "3" and lets us know how it worked.
Regards,
Prasobh