Did you mean: 

Capacity check at mass release CO05N

Former Member
0 Kudos

Hi all,

I have maintained stop release if there is a capacity constraint and material shortage.

System is working fine for individual orders (C002) however if i am executing mass processing (CO05N) system is giving message for material shortage , but no message for capacity constraint.

Please guide.

Sipra

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sipra

Did you maintain in OPJK capacity check , if you have given it shd message for capacity also

Cheers

Bala

Former Member
0 Kudos

Hi Bala,

I have maintained tahts why am getting warning message that capacity is unsufficent when i release order individualy but in mass release am not getting this message.

Regards,

former_member196398
Active Contributor
0 Kudos

Sipra,

Have you maintained "3" for Capacity in Check Control or "1", I think you have maintained one, since it is mass processing user interaction/interface does not take place and system releases with just a message in the logs for mass processing.

Please change the setting to "3" and lets us know how it worked.