on 10-15-2007 10:15 AM
Hi SRM gurus
we have BBP_GET_STATUS_2 in SRM with backgoround scheduled as follows:
1. Once every hour (with variant of 10days)
2. Daily once at 2am (with variant of 50days)
3. Once every week at 4am (with variant of 365days).
But from past 2 week the daily and weekly jobs been cancelled. Now the hourly job is also getting cancelled.
We are on SRM5.0 ECS.
with regards
Manjunath
Hi,
Ask you Basis team to check the table spaces related to ECC and SRM.
Thank you
Sreedhar Vetcha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
See the foll related threads:
related notes:
1078147 BBP_GET_STATUS_2: Error message E 002
1055375 BBP_GET_STATUS_2: Error message during conversion
1025350 BBP_GET_STATUS_2: Error message E 012
1051103 BBP_GET_STATUS_2: Error message E 007 in back end
1084987 Synchronizing documents and status between ERP and SRM
1062223 BBP_GET_STATUS_2: Performance and runtime error
1075526 BBP_GET_STATUS_2: No error message when back end is missing
1078692 BBP_GET_STATUS_2: Error message E 010, no follow-on docs
691569 Error messages in BBP_GET_STATUS_2
878654 BBP_GET_STATUS_2 performance: Enhancement around period
BR,
Disha.
<b>Pls reward points for useful answers.</b>
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Manjunath,
Is there any error message in ST22,SM21,SM37 ? Please run it in dialog process and find the error message.
Regards,
Masa