on 10-15-2007 9:52 AM
Hi guys!
I have following problem:
One material with a quota from 01.01.2008 to 31.12.9999
and the quoted amounts are okay.
The purchasing requisition before December work fine, the
field purchase organisation is filled.
But when I take a look at PR from December 2007 the purchasing
organization is missing.
What could be the problem?
Thanks for help,
Barbara
Hi,
Please check the source list, whether the validity period exists for December 2007 for that material and the Purchasing organization combination.
Regards,
DilliB