cancel
Showing results for 
Search instead for 
Did you mean: 

Cost element is not assigned to cost component structure

Former Member
0 Kudos

Hello All,

Can anyone tell me where should do the configuration for the message"Cost element is not assigned to cost component structure".?

Suitable points will be rewarded.

Thanks in advance

Regards

Srini

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Srni,

Pls assign Cost elements in your cost comonent structure.

T-coed:OKTZ.

Select you cost component and assign teh cost elemetn interval

Best Regards

Ashish Jain

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Srini,

You can assign it in tcode oktz.

Hope you've created a secondary cost element.