Change planning strategy

Hi all,

My client do not use planning in SAP normally. They manually create planned orders. They will start to use strategy 40. Sales orders already created will not have the correct requirement type, so existing sales orders must be maintained correctly. Is there a program that makes this change in a massive way?

Thanks,

Ergul

Former Member
Former Member replied

Ergul,

To my knowledge there is no possiblity of changing Requirement type in Sales order in MASS.

<b>Any how try transaction MASS with object type "BUS2032".</b>

Regards,

Prasobh