cancel
Showing results for 
Search instead for 
Did you mean: 

set up cost

Former Member
0 Kudos

Hi all,

Set up cost -


>Rs.100

Machine cost/pc -


> Rs.10

Component Cost/pc -


> Rs.5

Total : -


>Rs.115

In my material master, after costing run only machine cost and component cost are captured that is Rs.15 but my machine "set up" cost is not captured in the material master after Costing run (ck24) but it is captured in material cost extimate t.code ck11n.

Reason pls..

User

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member188826
Active Contributor
0 Kudos

If you are viewing the cost from cost component layout, confirm if the cost element for setup cost, has been assigned under the right component.

Former Member
0 Kudos

Hi,

Good afternoon and greetings,

Please check up the Routing and also the Work Centre for that particular activity type's inclusion in that and also check KP26 price planning for that activity type.

Please reward points if found useful.

Thanking you,

With kindest regards

Ramesh Padmanabhan

Former Member
0 Kudos

Ramesh

I have already maintained all the things stated by you.

Suggest other ideas pls.

user

Former Member
0 Kudos

Hi,

Good evening and greetings,

Please check up the Costing Sheet. The Setup Cost should have been defined as either a base or overhead type. If it is defined as an overhead type then a credit is mandatory and if that is missing then you may not get the setup cost in the calculation.

Please reward points if found useful

Thanking you

With kindest regards

Ramesh Padmanabhan

Former Member
0 Kudos

Problem Solved

User

Former Member
0 Kudos

Have you planned set up hours in kp26?

Former Member
0 Kudos

yes