Error in account determination while creating shipment cost document in SD

Former Member
0 Kudos

Dear all,

I have come across a case where an error has come in determining account while creating shipment cost document. This is happening only in the case of a particular shipment cost type. The Status of " Calculated" is C, the status of " Assigned" is " B" and the status of "Transferred" is A.

Can any one throw any light as to why it is happening like this?

Thanks and best regards

Kumaran

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear all,

With the help provided, I am unable to resolve the issue.

Any further inputs please?

Thanks & best regards

Kumaran

Former Member
0 Kudos

Hi,

Can you check related PO and also check is the system generating service entry sheet while creating shipment cost document.

Regards,

Chandra

Former Member
0 Kudos

hi,

Can you check the SAP note 740854 which may help you.