hi

because short ship, some order qty still open, how can i mark this SO is completed? Thanks

delivery block?

reject reason?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you can reject the balance quantity in the sales order as rejected so that the document flow will show as completed

Answers (4)

Answers (4)

Manoj_Mahajan78
Active Contributor
0 Kudos

Hi..

For balance quantity enter reason for rejection & save...

Reward IF U FINDS THIS AS HELPFUL...

Regds

MM

Former Member
0 Kudos

hi

any other method without mark reject reason?

Former Member
0 Kudos

Hi,

The only wayout other than 'a reason for rejection' is to change it to completed in the debut mode of the order. But you will need the help of a good ABAP consultant. But by rejecting the balance quantity with an appropriate 'reason for rejection' is the safest method.

Prase

Former Member
0 Kudos

Hi

U can create new reason for rejection for this may be as short shippment. and assign that reason for rejection in the sales order.

Muthupandiyan

Former Member
0 Kudos

Hi Jo,

Use the reason for rejection to close the orders.

Regards

Nadarajah Pratheb