Subcontracting with BOM

Former Member
0 Kudos

Dear all,

Can anyone tell me the method of creating PO with BOM

i mean what are the additional fields should be maintained in Material Master???

How to create Material BOM using Tcode CS01??

Is CS01 Tcode is for to create for maintaining Bill of Materials for a Finished product??

pls tell me in detail step by step to Create BOM and subcontracting BOM

Thanks a lot in advance??

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

If u want to use subcontracting with BOM, then

1) First create BOM for parent item in CS01

In BOM first you have to enter parent item that is going to be supplied by vendor, Enter Plant, BOm usage 1, Valid from 1900/01/01 so that validity problem will not be there.

Enter...

Then in ICT-item category enter L,

in component enter material which is going to be supplied to vendor by you, qty..and then SAVE

2) Create PO for parent item with item category L

3) In item data tab new tab will appear i.e. components...if u click on that it will show you the BOM.

regards

Umesh

Former Member
0 Kudos

Thanks umesh/Ravi

I'm able to create SC with BOM and got it what exactly CS01 Tcode is....

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos

Sub Contracting Cycle

(1) You have a material that can be procured externally, and you have maintained BOM with components. Any waste generated and received during subcontracting process can be maintained as component with negative quantity.

(2) You create a subcontracting PO (PO with Item Category L). You can also maintain Purchase Info Record for Subcontract category for material and subcontractor.

(3) You make a transfer posting to issue components for SC PO. Material is sent to subcontractor. As material remains under your ownership, system does not make any value entry. But quantity is shown as "Material Provided to Vendor"

(4) You receive finished material against SC-PO. You also specify components consumed in manufacturing of finished goods. Additionally, if you have negative components in BOM, now you'll also receive subcontracting by-products. There are three events, so three accounting entries are generated:

DR FG Stock/ SC By-Product Stock

CR Change in Stock (FG/ SC By-Product )

(for finished goods received)

DR Subcontracting Charges

CR GR/IR Clg

(for moneys payable to Subcontractor)

DR Consumption (Components)

CR Change in Stock (FG/ SC By-Product )

(material provided to Vendor is now charged to expense)

(5) You do the IV for SC Invoice, and the process is complete.

Process of Subcontract in MM

Sub-contract business process:

You want to buy material from the supplier (processed material/ assembled item) , but for some reason (quality of certain item / price ) you will give some component to vendor .

Vendor shall process the item / use the item provided & supply the final item.

SAP process:

1.Create the finished goods material code.

2.Maintain the BOM for the material.

3.Create PO with item category as "L" .

4.Issue material to vendor with movement type 541

5.Receive the material against the PO with movement type 101.

6.MIRO to account for vendor's invoice for the service charge& material used by him.

Can anybody tell me how a process has to be given to subcontracting?

Suppose, I have 3 operations 1)weaving 2)dyeing 3)cutting & packing

if no 2 process (i.e Dyeing) has to be given to subcontracting, what process should i follow ?

The following process to be followed for subcontracting.

1. Item code(material master) to be created at the stage of before dyeing.

2. Item code(material master) to be created after Dyeing as subcontracted item.(F30)

3. Bill of material to becreated for the material(2) calling for material(1)

4. Inforecord and source list to be created for material(2) with the corresponding vendor

5. PO to be released for material (2)

6.Along with PO the material(1) to be issued to vendor

7.On receipt of material when GR is made the stock with vendor will get updated.

How to Create a Subcontract Order?

To create a subcontract order, proceed as follows:

Enter the material you want to order and the item category for subcontracting (L) in the order item.

Press ENTER to display the screen for component processing.

Enter the components that the vendor requires to manufacture the product.

Please note:

– You do not need to enter the date required for the components. This date is proposed by the system when you press ENTER.

It is calculated as follows:

Delivery date of the item - Planned delivery time

– If you do not want the quantity of the components to be changed if the order quantity of the end product is altered, set the indicator Fixed quantity (column F).

– You can determine whether the components are available on the date required by selecting Edit -> Availability check.

If you entered a bill of material as the material in the subcontract order, the components are created automatically.

If you want to determine the components in the bill of material at a later date (for example, if the bill of material is subsequently changed), choose Item -> Component -> New BOM explosion. The existing components are deleted and redetermined in the bill of material.

Save the purchase order.

When you print the purchase order, the components are printed per order item

Subcontracting - Key Points

Special Procurement Process.

Item category: L

Order type: NB

In info record vendor should be maintained as subcontractor.

Vendor (Subcontractor) receives the components used to manufacture a finished product directly from your company or through third party.

Your company should place a purchase order for the finished product. In this manually you can enter the required individual components or it can be determined via the explosion of BOM (if exists).

Stock check at vendor level: ME2O

Company stock check: MMBE

GR for individual components through movement type: 501 or 561 (if with out PO or without reference).

GI to subcontracting vendor: through movement type 541.

GR from sub contracting vendor: through movement type: 101

Movement type 543 is displayed to cancel the material cost account.

If the subcontracting order has to be generated through materials planning,the special procurement key has to be set in MRP 2 screen.

- To create the Subcon Info Record : Tcode ME11 - Info Category - Click Subcontracting

- To create Material BOM : Tcode CS01

- With the Info and Material Setup, you can then create the Purchase Order in Tcode ME21N

Regards

Ravi