Hi,

My client has a requirement whike subcontracting. The client has to give the batch numbers to sub contractor at the time of giving subcontrctor PO , so that while physically recieving the Goods the batch numbers should be there in the label. The client is into food industry.So while doing GR for finished product these batch numbers should come. So at the time of PO can I mention batch numbers and GR to be done with same batch numbers.

regards

Ashok

Accepted Solutions (0)

Answers (2)

Answers (2)

csaba_szommer
Active Contributor
0 Kudos

Hi Ashok,

When you issue a PO you can give the batch number for each item. Isn't it good for you?

BR

Csaba

former_member218067
Active Contributor
0 Kudos

Hi Ashok,

Refer to below mentioned thread

https://forums.sdn.sap.com/click.jspa?searchID=5889575&messageID=3928894

BR

Diwakar