Actual cost showing doubled after settlement in PS reports

former_member219195
Participant
0 Kudos

Dear friends,

I have created a project with actual cost 120,000, and then I settled the cost to the AUC using CJ88 , when I run the report S_ALR_87013558 it gives wrong amount and counted the cost double 240,000 (120,000 + 120,000 )

This actual cost error is showing in all the reports plan, actual, budget etc.

Pls heip me for the solution

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hai Madhusudhan

Can u tell fm where the actual cost is picked up? Can u explain the scenario?

Regards

PP

former_member219195
Participant
0 Kudos

Dear friends,

We have done corrections as per SAP note: 666152 and problem is resolved.

Thanks,

Madhu

Former Member
0 Kudos

Please run the program BPDIST00 and then run transaction CJEN.

And check the consistency of value category assignment.

Thanks,

Sudhir

Message was edited by:

sudhir more

Former Member
0 Kudos

Hi,

Please check your settlement profile details. You can check after settlement, the debit / credit as after settlement the cost is getting doubled.

Hope this will help you.

Regards,

Rakesh Pradhan

former_member219195
Participant
0 Kudos

Hi sudheer,

Thanks for the reply.

CJEN executed still problem persists.

Former Member
0 Kudos

Hi,

Run the transaction CJEN for this project to reconstruct project info database.

Sudhir