I am working on KANBAN process.i have created some control cycle

In the transaction code PK13 i am putting only plant number and after execution it dispalying the KANBAN board with material status detail. But same plant number when enter in the PK12 transaction it giving error that no data found.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

PK13 demand source overview and once plant no is given it without any demand source it gives list of all the demand souces and the kanban statsues in that plant.

PK12 is supply source overview, in the radio button side select the issue plant and enter the plant it will fetch you the required results,