Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Info package

Hi,

I created a process chain that loads from an ods to cube both are full loads.

i included the Full load info package for the cube but when i run the Process chain the system creates 3 more info packages to the info source which are Init Delat and full and the process chain loads a Init load that the system created and then the Full load that is in the process chain. so when i look at the contents of the cube i always have 2 similar records.

Can someone help me fix this issue.

Former Member
Former Member replied

If u have request 1. request 2 in the DSO n u run a Full to Cube from DSO it will pull both the requests ( 1 + 2 ) - There may be aggregation of data though.

If on the next day request 3 comes n sits in DSO - a delta load from DSO to Cube will only pull request 3.

0 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question