settlement should be done with out TECO

hI,

in my case i produce material for a long period of time for a production order.

for example

production order quantity is 100 but i produce partial quantity every week but i do settlement every day for that production order. but every time i have to do TECO for that production order to settle at that time which is practically not possible.

so with out doing TECO for that order can i do settlement every day . if so how can i do . any setting have to be maintained