Hi,

in my case i am having a production order with 4 operations.

0010 milling

0020 winding

0030 cutting

0040 milling

among this opearion 0030 i want to do it in a plant which is assigned to different company code than mine.

in this case whether i should proceed with PP01 Control key with opearion plant as that plant which is lieing in diffent company code or

i should specify PP02 control key saying that plant as an external vendor for me and do PR and PO for that service .

which should i follow for my case and how cost gets updated .