Stop netting for semi finished materials

Hi all,

We are still using 46C. We have finished goods that are configurable and we use SUPERBOMs to pick the component that go along with the finished goods. I have a requirement where I have to stop the netting process for some semi finished materials in a certain storage location. We currently use strategy group '40' for semi finished.

I tried to use storage location MRP indicatior (MRP 4 view, sloc indicator). By doing so MRP stopped the netting which is what I wanted but it also stopped creating any new planned orders.

I want planned orders to be created but MRP should not read the stock. For example if the requirement is of 10 pcs and I have lets say 6 in stock, I still need planned order of 10.

I am more leaning toward writing a Z program to wipe out the inventory every night before the MRP run but was curious to see if there is any strategy group that I can use on the components to satisfy my needs.

Thanks a lot for your help.