Hi All
What happens if I give Dunning intervals in days 2 (dunning levels 3)
under dunning levels tab
days in arrears 10 22 33
what is the business impact?
Regards
Prasad
All Dunning does is it looks at the open accounting documents.
It then looks at all of those that have a Dunning Procedure and checks for blocks at a customer and line item level.
Then it works out which items are overdue and which of those could be dunned.
So if a group of invoices were 22 days overdue on a certain day they would be picked up on a Dunning run made that day.
Becareful as if you have also got other invoices that are say 34 days overdue, it will create a different dunning letter for them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.