MAP & standard price

Hi all,

I want the clarification on the following points regarding the MAP & standard price?? If anybody can reply

1) When is the MAP in the material master updated??

2) Is it updated for the Goods Receipt for the process order? OR is it updated only for a purchase order??

3) Is it updated for the process order created for the sales order through a planning run md50 (planning for a sales order---MTO scenario). I mean a sales order stock is directly created from the process order.???

4) When a GR is made for a STPO (stock transfer purchase order), how the MAP is updated in receiving plant??? AND WHEN.

If anybody can divert his valuable time to explain me the above..........

Regards,

Manish

Former Member
Former Member replied

Hello,

Pls finds some answers for questions raised by you

1) When is the MAP in the material master updated??

Answer: <b>MAP in material master updated when

MAP is nothing but value/Qty, so if there is change in any value during GR or Invoice verification, value of MAP in material master gets changes.

Reansons for value change is Variances in price.and change in quantity</b>

2) Is it updated for the Goods Receipt for the process order? OR is it updated only for a purchase order??

Answer: <b>It is get updated only for purchase order prices.</b>

Regards

Kedar

0 View this answer in context

Helpful Answer

by