Dear all,
we use AR to create the project and follow the following steps:
We created a project AF-0516031 and built the structure as follows. Level one WBSE is not account assigned
At level one WBS, project team member is assigned.
Network was created
In Level 2 , two WBS elements AF-0516031 .01 and AF-0516031 .02 was created, acc assignment indicator on
An activity was created for each WBS element
We saved the project
When we open the project again , only the level 1 WBS and the network is seen
if we go to CN41, we can see the activities but not the 2 WBSE created. I we click on one of the activity for detail screen WBS number is showing as <<<PR99999999>>>
now, If we try to create another WBS in level 2 in CJ20N, it is picking up the same number which was created earlier i.e., AF-0516031.01 and if we create an activity under this WBS, it takes the number as 0030 and the activity which was created earlier as 0010 appears before this activity.
Apart from this we are also getting errors like
After doing all these activities, we are getting different types of errors while Saving the project. Sometimes Abap dump is coming after we assign project team member to the WBS or sometimes system gives error that 1) "No status object is available for NWA #5" or, 2) "No status object is available for NWA #3" or 3) "No status object is available for NTW %00000000001"
Hi,
Please go thru SAP Note No.s 94699 & 678522.
94699 will solve ur problem
Thanks
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.