Regarding Subcontracting of Maintenance Spare..............

Hello Everybody........

The scenario of my question is like this.......

In my plant there is a machine which is also an asset.......when this asset was purchased by the company......there was no BOM attached to this. After some time, this machine came under breakdown & maintenance person removed one of its part say SHAFT. To reuse this shaft, it needs to be repaired by external agency. There is no other shaft available in the stores to use in this breakdown. Now as this shaft is not maintained in the store (neither as an asset nor as a material), then what will be the procedure to send this shaft to subcontractor.........Material Master for shaft can be created but what abt inventory stock.......

Regards,

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question