hi,

I have a subcon po with BOM component

example

1 pcs product A consist of 1 pcs product B & 1 pcs product C (BOM)

10pcs product B = 1 carton product B

10pcs product C = 1 carton product C

I created a subcon of 105 product A

so i need to issue out 105 product B & product C each or 10.5 carton each

It is possible for R/3 to round out to nearest carton , how to do it at sap . so both product B &C will be round up to 11 carton

regards

Accepted Solutions (1)

Accepted Solutions (1)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

Go to Change of Material Master (MM02) ie....product "A",product "B" and Prodsuct "C" each and enter selling unit if you are selling or order unit if you are Purchasing and maintain conversion factor with respect to base unit of measure.

( Example: Base Unit of Measure "PC" and Orde unit CARTON is "CT" and Enter the factor for converting the alternative unit to the base unit ie.. 1 carton = 10 PC) and save.

Now try your transaction and it will work.

If helpful then reward and close the thread.

Regards,

Biju K

former_member218067
Active Contributor
0 Kudos

Hi,

Please go to SPRO>SAP Netweaver>General settings>check units of measurements>select No dimension>press units of measurements>select carton >go to details here you have to put decimal place rounding

make it zero and try

Best Regards

Diwakar

reward if useful