Delivery Date not Set for Production Orders

Hi,

I am trying to settle a MTS (make to stock) production order that is both CNF and DLV. When I try to calculate variances, I get a KV 239 message stating that the delivery date is not set. I set this order to TECO and went to recalculate WIP but the production order cannot settle because this error still remains. When I drill down on the error, it states that there was an error in the program which set this order to DLV status, when no delivery date has been set. I can't see where this is looking for the delivery date. Has anyone come across this issue and if so, how would I go about correcting this?

Thanks!