conversion of material

Former Member
0 Kudos

Hi All,

Material type needs to be changed from HALB to HAWA. But there are open Production orders & also for some of the orders are partially confirmed.

Please let me if it is possible to change the Material Type, if the current open production orders are closed.

regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can change it.

Close the production order.settle it. If there is any planned order for that material, delete it. check for the nil stock.

Regards,

satyajit

Answers (2)

Answers (2)

former_member196398
Active Contributor
0 Kudos

Suman,

So were you able to change the materail type with PP orders in TECO or CLSD status still avaliable in system? Your answer will help others.

Regards,

Prasobh

Former Member
0 Kudos

Hi all,

Ya it is done sucessfully.Prod. order was TECO"d and closed and planned was deleted. Stock was cleared.

Thanks all for your input.

Regards,

Former Member
0 Kudos

Hi,

Yes, it is possible to change the material type from HALB to HAWA .

As per your statement,have to close all the open & partially confirmed production orders has to settle.

Nil Stock has to maintained and UOM also check it.

Regards,

Raja

Former Member
0 Kudos

Hi

partially confirmed production orders has to settle.?HOW TO DO THIS?

REGARDS

Former Member
0 Kudos

Goto process order > functions > restrict processing > techincally complete

to settle the order.

Karthik

Former Member
0 Kudos

Open the production order CO02 and do TECO . After that settle the order as a regular procedure.

Regards,

Raja sd