conversion of material

Hi All,

Material type needs to be changed from HALB to HAWA. But there are open Production orders & also for some of the orders are partially confirmed.

Please let me if it is possible to change the Material Type, if the current open production orders are closed.

regards,

Former Member
Former Member replied

Hi,

You can change it.

Close the production order.settle it. If there is any planned order for that material, delete it. check for the nil stock.

Regards,

satyajit