BAdi to change fields in cProjects

hello!

I need to add new fields to the cProjects 'task' and 'projects' dashboards and fill them with data from other similar fields.

But I am not able to figure out where the existing fields are being populated so that I can pass those values to new fields. I tried external debugging to see if it hits BAdi i can use. But only one BAdi was hit and that had no changing parameters and not all needed fields were present.

Can anyone tell me which BAdi's are triggered for cProjects? Or is there any way other than BAdi's to fill data into new fields?

thanks a lot in advance!

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question