on 08-18-2005 5:02 AM
Hi all,
We have two seperate hosts having WAS servers each(central instance in each machine) . We are trying to acheive high availability and Load Balancing mechanism.
Can anyone sugggest me a way in order to acheive this type of scenario.We have central instance on each host . Assume if one central instance on one WAS server fails, the other should take over the failure.
I am not talking abt one central instance in one host and multiple dialog instance in diff hosts.. We need to achieve High availability & Load balancing with this tech infrastructure setup.
Regards
Vasu
Hi,
Refer this link from help.sap.com & sublinks thereafter.Surely it will be helpful to u.
http://help.sap.com/saphelp_erp2004/helpdata/en/b5/e8239ef7bd494f896a84625d4b688f/frameset.htm
Rdgs,
G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the following link
for failover you need MSCS(recommended)
http://help.sap.com/saphelp_nw04/helpdata/en/c4/3a644c505211d189550000e829fbbd/frameset.htm
regards
anand.M