Hi,

Can anyone help me with how to create a transport in IP.

Thanks

Rex

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

All IP objects will be transported thru transport conenction in RSA1.

RSA1 - transport conenction - Planing. Collect the aggregation levels to the sequence here and transport. Also, you need to collect the cube before the planing objects.

Ravi Thothadri

Former Member
0 Kudos

Hi Rex,

in addendum to the above pay attention to the following:

New objects need to be transported as indicated above. Changes to existing objects will be automatically included in the "BEX request". This is a transport request one always has to assign in the transport connector (icon "BEX" followed by a truck). If no BEX request has been assigned, one cannot save changes to objects which already have been transported at least once.

D

Answers (2)

Answers (2)

Former Member
0 Kudos

That was very helpful.

Thanks

Rex

Former Member
0 Kudos

Hi,

you have to transport IP via the transport connection in BW...

You drag the items to the right -> make transport request -> transport

Ciao

Joke

Former Member
0 Kudos

In the list of objects on the left in the transport connection, you will get a folder called planning inside which you will get all the planning objects. You can search for those which you want to transport and collect them in transport requests.