Good Day.

I have a scenario as follows:

FERT: 1001

ROH: 2001

When I create sales order for FERT 1001, when I run MRP, I want the system to create planned order or PR for ROH 2001, same quantity as 1001.

Let me know which BOM usage should I use?

We will not use PP/production order for this. Just Sales Order and Purchase Order.

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

rmazzali
Active Contributor
0 Kudos

I think you need a production BOM and a production order. Then the production order transfer the requirment to the ROH material.