on 10-09-2007 1:33 PM
Hi all,
I have a question with regard to scheduling of dependent requirements. At my current company we produce semi finished goods and finished goods. When I create a Planned independent requirement for the finished good and run MRP, then a planned order is created for the semi-finished good as well. The problem is that the planned order for the semi finished good is scheduled at exactly the same time as the finished good. So both production are scheduled in parrallel. What I want to see is that both orders are scheduled sequential, first the semi-finished good and once this is produced, then the finished product.
Where can I make these settings?
Will reward points for useful answers,
Kind regards,
Mark
Can you tell me what settings are there img
OPU5 - What is the scheduling parameter for the combination of plant and order type(= * )
what is the scheduling type?
start in past = ?
In BOM of header material, halb material is a item
In this material item detailed view
In basic data
in MRP data
what is given in lead time off set and operation op off set?
just check this and come back with the data so that we can answer your question in a better way
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok, then the solution is as below
When the system schedules les us FERT, as per routing let us its lead tome is 30 days for 100 EA
Same for HALB, production time is 30 days for 100 EA, as per BOM for 1 fert-1 halb is required.
Now system schedules first FERT. its requirement date(from sales order or PIR delivery date) is lets say 09.12.2007.
hence FERT should start production on 09.11.2007 so that as per scheduling it will finish on 09.12.2007. HALB should be produced by 09.11.2007, but start date as calculated by scheduling is 09.10.2007, hence system will switch over to (it is std sap behavior if past days in scheduling is empty) forward scheduling and i starts from today i.e. HALB if starts today, it will end on 09.12.2007.
Now this is the situation what I can read from the data you have given, just check and come back
Sorry for my late reply:
First of all, there are no PIRs for HALB materials.
In my test-case the situation is as follows:
FERT: Start: 31-12-2007 at 02:59 - End: 02-02-2008 at 24:00
HALB: Start: 31-12-2007 at 0:00 - End: 31-12-2007 at 16:36
So the date basically works, but the exact times do not match
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It looks like in FERT it is backword scheduling as it starts from 24:00:00
HALB it is forward scheduling as it starts from 00:00:00
It looks like HALB and FERT are in different MRP group and in MRP group level Scheduling paranmetres are different
Just check in Matreial master MRP1 what is the MRP group for FERT and HALB same or different?
In the production order- did you run rescheduling?
Please se in the production order of HALB and FERT in the order header tab page...what is the scheduling type?
I simulatedv the data, what I found that as per planned order everything looks okay, when after production order creation when I changed the sheduling type and resheduled it..it is the same result i am getting...
Hi Hogewoning
Reran MRP for that material with option schduling : Lead time scheduling
Cheers
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.