I had created a project with WBS element and Activity
and Planned cost of Rs.75000/- and same copied to Budget and saved
Project status is BUD AVAC
in tolerance limit i given control on PO 100% if exceeds a error message
now i assign a material to activity and release the project PR number generated
wrt that created a PO with value Rs.100000/- which came from Material master this the assigned value
now if u increase the value from 101000/- it is giving a error message
now the problem is our scenario is to consider the Planned cost but not the assigned values
Please give the solution it is very urgent
First commitment management should be activated TC-OKKP. second by TC OPSV, network category Appended indicator have to set for appending network plan value to WBSE and Fund commitment indicator also required to set.
Thanks,
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check the WBS element status for which the procurement is made, if it is with out BUDG AVAC, system shall check for the next higher level WBS element with these statues and if the budget is available there then it will allow even if the planned value at the lower level WBS element is less than the procurement amount.
Regrads
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It seems the plan cost is not getting assigned to WBS. Please check in TC: OPSV, for order type 20 ie network, whether the relevant check boxes are ticked or not.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Budget functionality is working properly in your case. As an amount of Rs.7500/- is budgeted so on exceeding this, system will n't allow to release purchase order. I assume Planned cost has n't taken into account price from material master. In the material master moving average price is to be considered, for releasing the purchase order. If your scenario required planned cost, then it should be inline with material master moving average price. Please Plan the cost of project as per material master which will be transfered to the budget.
Hope this will clarify you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.