Budget control at PO stage in Projects ***urgent***

Hi Experts,

Plz solve this scenario

I had created a project with WBS element and Activity

and Planned cost of Rs.75000/- and same copied to Budget and saved

Project status is BUD AVAC

in tolerance limit i given control on PO 100% if exceeds a error message

now i assign a material to activity and release the project PR number generated

wrt that created a PO with value Rs.100000/- which came from Material master this the assigned value

now if u increase the value from 101000/- it is giving a error message

now the problem is our scenario is to consider the Planned cost but not the assigned values

Please give the solution it is very urgent