on 10-09-2007 8:40 AM
Hi ,
I am facing 2 issues while generating SNP Production Plan through SNP Optimizer
1) Production Plan is in decimals ( Although in CUNI i have maintaine EA as 0 decimals allowed) while running SNP Optimizer.
2) There is a break in Production ie. SNP Production Plan for a give SKU is not continuous like it is on 1st bcket 5th bucket 10th bucket then from 15th to 25th it is continuous and again from 26th onwards thr is a break in production.
Thanks in advance
Abhishek B Somani
098767330822
Hi Abhishek,
For the 1st issue, check your planning area via /sapapo/msdp_admin. Go to key figures tab and click on details. Find the key figure for Production Plan and check the defined decimal places there.
For the 2nd issue, optimizer will not necessarily recommend production at the desired buckets. Optimizer can opt to prebuild or delay production depending on your cost structure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
IN CUNI, you can always maintain display units as 0 and keep Decimal Pl. Rounding also as 0. This should be enough to get rounded plans.
For the second one, check the behaviour by reducing the lot size. It may be a possibility that the higher lot sizes are influencing the optimizer to produce intermittantly. Possibly these lot sizes are comparable to the capacity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.