qm inspection lot

we have problem iselect inspection type 03in qm tab in material master also menton mic in routing after creating production order inspection lot is created but in inspection lot there is error that inspection specification not yet assign what is solution ple send reply

Former Member
Former Member replied

Dear, please check the following

In Material master, QM view in the insp type 03 details

check box-insp with material specification

Check box-insp with task list

In the above check box, which one ticked?

If both are ticked then you need to maintian material specification in QS61, or remove this tick from check box-insp with material specification in material master

Check routing is valid as per the validity, lot size etc.

then goto Qa02 and goto insp specification tab page

Click on task/spec push button.

Please come back if you donot get the solution