Can anyone explain me what is Attribute Changerun, in detail, Urgent

Former Member
0 Kudos

Can anyone explain me what is Attribute Changerun, in detail

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

When you load data to attribute table of an infoobject( P Table) the new records will get added to table with Object version "M".

But during reporting only the records with Object version "A" (Active) will be displayed.

To update the old records (Object version "A") with the newly added records ( with Object version "M") you have to execute attribute change run.

You can see the changes in the P table (Goto SE11 and you can see the attribute table of an infoobject).Suppose your object name is ZMATNR then the attribute table is /BIC/PZMATNR. See this table before attribute change run and after attribute change run.

Award points if this is helpful.

Regs

Gopi

Former Member
0 Kudos

Hi Gopi,

Thanks for your valuable answer

points alloted

Answers (2)

Answers (2)

former_member228339
Contributor
0 Kudos

If you assign the process type Attribute Change run to a process chain you must define a variant. With this variant you have to define the InfoObjects for which you want to activate the master data. There are four different possibilities:

­ HIERARCHY: direct selection of the hierarchy which need to be activated

­ INFOOBJECT: direct selection of the infoobjects which need to be activated

­ LOADING: indirect selection: reference to an InfoPackage, which must be loaded before in the process chain. Combined with the meta data of these objects and the instance information the system derives the affected InfoObjects and hierarchies. If the chosen LOADING object is not in the process chain, the system automatically inserts the chosen infopackage in process chain.

­ REPORTVARIANT: indirect selection: reference to a change run variant which you can define with RSDDS_AGGREGATES_MAINTAIN (SE38) or TCode RSATTR Executing the Attribute/hierarchy change run with Variant:

Instead of applying the InfoObjects or hierarachies directly to the process variant in RSPC you can create a central variant for the report RSDDS_AGGREGATES_MAINTAIN. You can assign InfoObjects and hierarchies to this report variant. This central variant could be used by several process variants in RSPC. The benefits are central maintenance, ..

Former Member
0 Kudos

Hi Hari,

Thanks a lot for your suggestion

points alloted

Former Member
0 Kudos

Just search SDN u'll get ur answer in no time dude.

To update/activate changes done to master data so the same will be available for reporting.

Former Member
0 Kudos

Hi Roberto,

Thanks for your sugestion

points alloted