Hi Gurus
Problem.I have 4 vendors A,B,C,and D with quota of 40,30,20,and 10.The requirement is of 1000 pcs.The minimum qty for A is 400pcs.How the system will distribute the qty,Please explain it in detail as I am very new to this topic.
To begin with and assuming that
Quoata Allocated Qty=0
Quota Base Qty= 0
Quota Rating wil be 0 for all four vendrsas
Quota rating= (quota allocated qty+ Quota base qty)/Quota
Lowest quota rating is the effective source .
Since the quota rating is 0 for all , it will go to Vendor with heighest Quota which in this case is "A".
Quota Base Qty is used if a new source is included in the existing quota arrangement . The quota base qty enables you to prevent a situation in which the new source is assigned all requiremnet until its quota allocated qty exceeds the
quota allocated qty of any existing sources.
Hope it helps you.
Thanks ,
Tausif
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sam,
Ensure that you have created necessary Info, (ME11) Source List (ME01) and Schedule Agreement (ME31L).
Check whether the schedule agreement linked in source list with the MRP indicator.
Check whether the purchasing view filled with the quota arrangement data.
Check whether the MRP1 view is filled with necessary MRP Type.
Create Quota arrangement by using transaction MEQ1 and fill the validity end date to open the quota screen.
Fill the Procurement type, vendor code and quota split for the two vendors and run MD03 (MRP run).
You will get the splited schedule lines as per the quota and you can view it in MD04.
Minimum Quantity for Splitting Quota specifies for the splitting quota the minimum quantity that a lot must have in order to be apportioned among several sources of supply in the planning run.
If the lot is smaller than or equal to the minimum quantity, the system will proceed on the basis of the usual quota arrangement logic.
The indicator for the splitting quota must be set for the the lot-sizing procedure used for materials planning purposes in Customizing.
Regards
Rajesh
Do reward if useful...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.