Not to reschedule in the MRP run.

Former Member
0 Kudos

Hello!

I have product P000GR00000000 consisting a

component say B000GR00000000 .

If i create production order of P000GR00000000 for DATED 30.09.2007 of 100 EA.then order will reserved -100EA for B000GR00000000 & when i take MRP run it will generare plan order of 100 EA for B000GR00000000.Similarly if i create production order for P000GR00000000 for dated 30.10.2007 of 200EA.Then MRP run will generate 200EA plan order for B000GR00000000.

Now, i create production order for P000GR00000000 of 300 EA for dated 30.11.2007 & meanwhile the production order of P000GR00000000 DATED 30.09.2007 is technically completed then order reserved for B000GR00000000 of -100EA will be cancelled.If i take MRP run now ,then order reserved of -300 EA for B000GR00000000 will rescheduled,that i want to restrict.

Is there any solution Not to reschedule in the MRP run if order is TECO.

please give the solution.

regards,

mangesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Mangesh

You can define Rescheduling at plant level or MRP group level using OPPQ/ OPPR or OMDW. if you define at plant level then no need to create in MRP group and assign to material

secodly if you want to avaoid the Reschedule Exceptions then

You can define tolerance values in additon to Resheduling horizon. for the creation of exception messages, in Customizing. These values define a time period in which no exception message is to be created, despite the fact that a rescheduling proposal may exist.

If you don't want reschedule check for production orders then you can remove the flag against production orders in the firmed elements.

if you TECO the order Normally MRP should not consider while planning!

please check onesecond and come back

But Teco will allow you for posting (GR/GI)

hope this helps

BR

SK

Former Member
0 Kudos

There is a functionlaity called Rescheduling Horizon, when defined only considers those receipts with the period given.

We can give the Horizon as the time period in which the receipts to be considered for rescheduling.

Also which receipts Production orders or Plannined orders or firm orders or Reservartions can also be defined.

T.Code; OMDW for a plant or MRP group.

Reward if it fits your solution

Former Member
0 Kudos

thanks for reply

i tried tcode OMDW & OMDW for MRP group but its not working,if u have other

solution for the same please reply me

regards,

mangesh

Former Member
0 Kudos

Have you asssigned this MRP group to the material? After assignning it run the MRP.