Order Change Management(OCM) in SAP

Former Member
0 Kudos

Dear All,

OCM is applicable in MTO Scenario.

Kindly let me know the steps involved to activate OCM n how to proceed

further.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check the file from the following link and read from page 399.

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPSFC/PPSFC.pdf

Regards

Kannan

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bagchi,

Order Change Management is applicable for MTO/MTS Scenario,

<u>First:-</u>

In WorkScheduling View of Material Master (FERT/HALB or Any Defined for Production) you need to maintain "<b>Overall Profile"</b>

<i>This Overall profile should be configured in SPRO > PRoduction>Shop Floor Control > Operations>Change Management for Production Orders--><b>Define Overall Change Profile</b>.</i>

<u>Process of OCM follows this way:</u>

Create a Change Number <b>CC01 with Release</b> Key

In Object Types select/tick "Actv", "object", "MgtRec",

You get the Change Number by Saving .

Use this Change Number to Change BOM or Routings

<i><b>Then Release the Change Number useing Release Key till then you don't find the Change of BOM in Production Order.</b></i>

Then go to Oder Change Process<u><b> T Code :- COCM</b></u>

Tick Change Number and Select the Change Number & Execute

Select the Production Order, click on “Procurement element” icon you get another screen select and execute again.

You get an Pop-Up screen. "Determine changes”, “Check changes”, “Change Original Order”.

you see the changes in BOM for Production Order i.e. after COCM.

Then Confirm the Changes in Production Order then New changes will be Active in production Order.

Regards

Rehman

<b>Reward Your Points If Useful</b>

Former Member
0 Kudos

Hi Rehman,

Based on ur guidance,I have followed all steps.Now,I have created a Prod. order and now I changed the BOM comp. qty. against a change no. and then released the change no. with released key '1'(Global release).

Then executed T_code:COCM,sel. criteria Change no.,Prod. order,but I don't get any prod. Order.Kindly help.Is OCM applicable to MTS also.or it works only with MTO.

Former Member
0 Kudos

Thanx Rehman .It works.I have rewarded you points.