I am trying to make a service order and i want to use two work centers , two activity types and two cost centers.
My problem is with the cost center.
When I am making DP90 I can see the cost center for each activity type - work center but in VA02 I have the same cost center for each component or operations(cost center for main work center , the one that I set in the header data of the service order).
What should I do to have the cost centers properly assigned ?????? It's very urgent.
Please help me!
Any help would be appreciated.
We work with 4,6C and we try to implement PM-CS module.
hai,
I thing you are using the following
Cost Center - KS01
Activity Type - KL01
Work Center - CNR1
In Activity type you want to assign Allocation cost Element
In work center you want to assign Cost center as well as Activity type.Pls make sure this assignments.
Pls assign Points if it is useful.
govind.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.