When we change the date and time of a planned order in ECC that is not reflecting in APO.In CCR there is no error.
Hi all,
I've met the same problem already, even when the product was included in the model and the model was activated.
I solved it by doing this STEP BY STEP, it's important :
- first desactivate the concerned integration model completely
- regenerate the model and save it
- then reactivate the model
The error should desappear or at least appear in CCR...
Hope this helps.
Fabrice
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Is the integration model active for the planned orders ?
Is the product in APO is in the active model ?
Vala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hopefully the Parameter IDs are not setup to conceal the time differences. It is usually sometimes a practice to setup Paramter IDs to hide these annoying small time differences.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
is it happening the other way round? changing in APO changes R3?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.